[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938765":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},938765,606,1,"单选题","下列投标的情形中，评标委员会应当否决其投标的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","逾期送达的投标文件",false,{"key":16,"text":17,"correct":14},"B","未按要求密封的投标文件",{"key":19,"text":20,"correct":21},"C","以低于成本报价竞争",true,{"key":23,"text":24,"correct":14},"D","投标文件中出现细微偏差的","本题考查的是开标、评标和定标。选项 AB 属于应当拒收的情况，选项 D 不充分，评标委员会可以书面方式要求投标人对投标文件中含义不明确、对同类问题表述不一致或者有明显文字和计算错误的内容作必要的澄清、说明或补正。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]