[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938744":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},938744,606,2,"多选题","施工招标项目工期较长的，招标文件中可以规定（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","工程造价指数体系",true,{"key":16,"text":17,"correct":18},"B","工期延长的具体规定",false,{"key":20,"text":21,"correct":14},"C","价格调整因素",{"key":23,"text":24,"correct":14},"D","价格调整方法",{"key":26,"text":27,"correct":18},"E","工程量清单计价模式","ACD","本题考查的是招标文件编制与发放。施工招标项目工期较长的，招标文件中可以规定工程造价指数体系、价格调整因素和调整方法。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]