[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938719":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},938719,606,2,"多选题","关于货物招标文件的说法，正确的有( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","招标文件中应标明拟招标货物的原产地",false,{"key":16,"text":17,"correct":18},"B","招标文件中必须提供拟采购设备的详细技术数据",true,{"key":20,"text":21,"correct":14},"C","招标文件中应对非实质性要求规定允许偏差的最小范围",{"key":23,"text":24,"correct":18},"D","招标文件中应载明主体设备进行分包的范围",{"key":26,"text":27,"correct":18},"E","招标文件中的实质性要求和条件应以醒目的方式标明","BDE","A.招标文件中应标明拟招标货物的原产地——不能标明 C.招标文件中应对非实质性要求规定允许偏差的最小范围——最大",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]