[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938706":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},938706,606,1,"单选题","下列关于招标各项工作期限的表述中，正确的是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","自招标文件发出至提交投标文件截止最短不得少于 20 日",true,{"key":16,"text":17,"correct":18},"B","招标人中标人应在中标通知书发出后 20 日内签订合同",false,{"key":20,"text":21,"correct":18},"C","应在评标委员会提出书面评标报告后 10 日内确定中标人",{"key":23,"text":24,"correct":18},"D","招标人应在中标通知书发出后 10 日内完成招标备案","B.招标人中标人应在中标通知书发出后 20 日内签订合同——30 日内 C.应在评标委员会提出书面评标报告后 10 日内确定中标人——15 日内 D.招标人应在中标通知书发出后 10 日内完成招标备案——15 日内",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]