[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938703":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},938703,606,1,"单选题","下列关于投标文件补充、修改或撤回的表述，错误的是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","投标文件的补充和修改内容应当密封，可以在投标截止日期之后送达",true,{"key":16,"text":17,"correct":18},"B","在提交投标文件截止时间后到投标有效期终止之前，投标人撤销投标文件的，招标人可以 不退还其投标保证金",false,{"key":20,"text":21,"correct":18},"C","在投标截止日期之后，投标人有权撤回已经送达的投标文件",{"key":23,"text":24,"correct":18},"D","投标人在投标截止日期之前放弃投标，招标人不得没收其投标保证金","投标人在招标文件要求提交投标文件的截止时间前，可以补充、修改、替代或者撤 回已提交的投标文件，并书面通知招标人。补充、修改的内容为投标文件的组成部分。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]