[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938623":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},938623,606,1,"单选题","项目经理进行全过程控制的关键，是对团队成员的工作进行有效的控制，实现有效控制的前提是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","进行合理的分工与适度的授权",true,{"key":16,"text":17,"correct":18},"B","建立和保持有效、畅通的信息通道",false,{"key":20,"text":21,"correct":18},"C","经常性的检查",{"key":23,"text":24,"correct":18},"D","及时进行必要的调整","本题考查的是项目经理。项目经理进行全过程控制的关键，是对团队成员的工作进行有效的控制，进行合理的分工与适度的授权，这是实现有效控制的前提。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]