[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938622":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},938622,606,1,"单选题","根据每位项目成员的技能和发展需要，分配项目职责，清楚界定每个人的任务和绩效期望值，制定接受标准，这是项目经理在（ ）阶段的工作。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","研究项目工作任务",false,{"key":16,"text":17,"correct":14},"B","编制项目工作计划",{"key":19,"text":20,"correct":14},"C","成立项目团队",{"key":22,"text":23,"correct":24},"D","项目启动",true,"本题考查的是项目经理。项目启动阶段，项目经理还要根据每位项目成员的技能和发展需要，分配项目职责，清楚界定每个人的任务和绩效期望值，制定接受标准。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]