[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938585":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},938585,606,2,"多选题","对组织内各岗位制定的考核标准包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","考核目的",false,{"key":16,"text":17,"correct":18},"B","考核时间",true,{"key":20,"text":21,"correct":18},"C","考核内容",{"key":23,"text":24,"correct":14},"D","考核结果",{"key":26,"text":27,"correct":18},"E","考核形式","BCE","本题考查的是工程项目管理组织的建立步骤。为保证项目目标的最终实现和工作内容的全部完成，必须对组织内各岗位制订考核标准，包括考核内容、考核时间、考核形式等。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]