[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938564":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},938564,606,1,"单选题","项目经理在组织进行项目工作分解时，应明确工作包内各工作之间的相互逻辑关系。根据需要可绘制（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","香蕉图",false,{"key":16,"text":17,"correct":14},"B","S 曲线图",{"key":19,"text":20,"correct":21},"C","项目网络图",true,{"key":23,"text":24,"correct":14},"D","工作分解结构","本题考查的是项目经理。项目经理在组织进行项目工作分解时，应注意以下几方面：确定关键的项目成果和里程碑，做出工作分解结构，并与项目团队及客户沟通；注意分解的方法；对分解出来的每一工作单元与工作包要明确相关指标与内容；明确工作包内各工作之间的相互逻辑关系，根据需要可绘制项目网络图。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]