[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938538":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},938538,606,1,"单选题","将同类项目的角色分工、职责和相互关系的确定作为今后类似项目的参考或依据，这是组织计划制订方法中的（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","模板",true,{"key":16,"text":17,"correct":18},"B","人力资源管理实践",false,{"key":20,"text":21,"correct":18},"C","专家评定",{"key":23,"text":24,"correct":18},"D","商业数据库","本题考查的是组织计划制订的方法与工具。将这些同类项目的角色分工、职责和相互关系的确定作为今后类似项目的参考或依据，就成为组织计划制订的模板。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]