[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938535":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},938535,606,1,"单选题","有关人员配备，下列说法不正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","人员配备计划描述人力资源何时加人项目工作及何时脱离项目工作",false,{"key":16,"text":17,"correct":18},"B","人员配备计划必须是正式的",true,{"key":20,"text":21,"correct":14},"C","人员配备计划可以是详细的或者是框架式的",{"key":23,"text":24,"correct":14},"D","人员配备计划是整个项目计划的一部分","本题考查的是团队组织计划。根据项目的具体情况，人员配备计划可以是正式的，也可以是非正式的；可以是详细的，也可以是框架式的。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]