[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938533":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},938533,606,1,"单选题","不属于工程项目人力资源管理组织计划内容的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","人员配备管理计划",false,{"key":16,"text":17,"correct":18},"B","人员奖惩管理计划",true,{"key":20,"text":21,"correct":14},"C","角色和职责安排",{"key":23,"text":24,"correct":14},"D","组织关系图表及说明","本题考查的是团队组织计划。组织计划通常包括四方面的内容：角色和职责安排、人员配备计划、组织关系图和有关说明",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]