[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938518":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},938518,606,2,"多选题","进行工程项目管理组织设计应考虑的主要因素有( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","项目规模、工作内容、工作性质",true,{"key":16,"text":17,"correct":18},"B","项目招标方式",false,{"key":20,"text":21,"correct":18},"C","社会公众的教育程度",{"key":23,"text":24,"correct":14},"D","项目的信息资源、人力资源等情况",{"key":26,"text":27,"correct":14},"E","国家法律法规要求","ADE","管理组织设计的依据 1.项目自身的特点。包括项目规模、工作内容、工作时间、工作性质、已有资源状况等。 2.承担项目任务公司的管理水平和对项目的管理要求 3.委托方的要求 4.项目的资源情况。项目资源包括项目的信息资源、人力资源、时间资源及资金资源等。 5.国家的有关法规",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]