[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938506":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},938506,606,2,"多选题","项目团队考核的方式包括( )。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","任务跟踪",true,{"key":16,"text":17,"correct":14},"B","平时抽查",{"key":19,"text":20,"correct":14},"C","阶段总结汇报",{"key":22,"text":23,"correct":14},"D","征求客户意见",{"key":25,"text":26,"correct":27},"E","领导评价",false,"ABCD","项目团队考核方式：1.任务跟踪。2.平时抽查。3.阶段总结汇报。4.征求客户意见。 5.问题征询。6.成员互评。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]