[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938481":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},938481,606,1,"单选题","在工程项目管理组织建立过程中，组织结构设计之后的工作是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","人员配置",false,{"key":16,"text":17,"correct":18},"B","确定工作岗位及职责",true,{"key":20,"text":21,"correct":14},"C","确定组织目标",{"key":23,"text":24,"correct":14},"D","确定工作流程与信息流程","本题考查的是工程项目管理组织的建立步骤。工程项目管理组织的建立步骤：确定合理的项目目标→确定项目工作内容→确定组织目标和组织工作内容→组织结构设计→工作岗位与工作职责确定→人员配置→工作流程与信息流程→制订考核标准。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]