[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938444":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},938444,606,1,"单选题","让处于项目团队计划执行中最末端的团队成员参与团队计划的制订过程，属于团队能力开发中的（ ）活动。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","改善工作环境",false,{"key":16,"text":17,"correct":14},"B","表彰与奖励",{"key":19,"text":20,"correct":14},"C","进行人员配合训练",{"key":22,"text":23,"correct":24},"D","开展团队建设性",true,"本题考查的是项目团队的发展过程。开展团队建设性活动，例如，让项目团队计划执行链中处于最末端的团队成员参与团队计划的制订过程；让那些没有管理能力和处理问题经验的项目团队成员参加制订暴露和解决矛盾的一些基本规则的过程；请一个没有主持过会议的团队成员主持一个5分钟的会议日程表调整会等。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]