[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938437":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},938437,606,2,"多选题","对团队成员进行有效的控制是项目经理对项目进行全过程控制的关键，重点包括（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","进行适度的授权",true,{"key":16,"text":17,"correct":14},"B","进行必要的调整",{"key":19,"text":20,"correct":14},"C","进行经常性的检查",{"key":22,"text":23,"correct":24},"D","做好对外关系的协调",false,{"key":26,"text":27,"correct":14},"E","建立和保持有效、畅通的信息通道","ABCE","本题考查的是项目经理。选项D，“做好对外关系的协调”与“对项目全过程进行全面控制”并列，属于平行关系。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]