[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938436":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},938436,606,2,"多选题","关于编制项目工作计划的说法，正确的有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","组织编制项目工作计划是项目经理的重要工作",true,{"key":16,"text":17,"correct":14},"B","项目工作计划是开展项目工作的规定性文件",{"key":19,"text":20,"correct":21},"C","项目工作计划的编制不受委托方影响",false,{"key":23,"text":24,"correct":21},"D","项目工作计划又称为项目工作大纲（TOR）",{"key":26,"text":27,"correct":14},"E","项目工作计划应包括项目工作进度计划","ABE","本题考查的是项目经理。选项C错误，应与项目委托方取得一致意见；选项D错误，委托方提供项目工作大纲（TOR）。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]