[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938433":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},938433,606,2,"多选题","项目团队正式开展工作以后，项目经理管理团队工作必须（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","编制项目工作大纲",false,{"key":16,"text":17,"correct":18},"B","对项目全过程进行全面控制",true,{"key":20,"text":21,"correct":18},"C","协调相关关系",{"key":23,"text":24,"correct":18},"D","对团队成员工作进行指导",{"key":26,"text":27,"correct":14},"E","关心团队成员未来去向","BCD","本题考查的是项目经理。选项A，应由委托方提供项目工作大纲（TOR）；选项E，属于项目完成后的工作。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]