[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938430":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},938430,606,2,"多选题","项目经理在整个项目执行当中的主要工作包括（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","建立工作基础",true,{"key":16,"text":17,"correct":14},"B","正式启动项目",{"key":19,"text":20,"correct":14},"C","管理团队工作",{"key":22,"text":23,"correct":24},"D","积极拓展并承接各类项目",false,{"key":26,"text":27,"correct":14},"E","项目结束阶段的工作","ABCE","本题考查的是项目经理。项目经理的主要工作：（1）了解项目情况，研究工作任务；（2）分析项目相关人员；（3）编制项目工作计划；（4）成立项目团队；（5）项目启动；（6）组织制订项目因队各项具体实拖计划。项目经理的团队管理工作：（1）开展项目实施中的指导；（2）对项目全过程进行全面控制；（3）做好内外关系的协调；（4）项目完成后的工作。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]