[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938404":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},938404,606,1,"单选题","单位工程开工前，( )必须向承担施工的作业队负责人、工长、班组长和相关人员进行 交底。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","单位工程技术负责人",true,{"key":16,"text":17,"correct":18},"B","总承包项目部",false,{"key":20,"text":21,"correct":18},"C","分包商",{"key":23,"text":24,"correct":18},"D","单位工程项目负责人","总承包项目的技术交底应逐级进行，总承包项目部向分包商交底，分包商向施 工人员交底。单位工程开工前，单位工程技术负责人必须向承担施工的作业队负责人、工长、班 组长和相关人员进行交底。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]