[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938385":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},938385,606,2,"多选题","质量计划的内容包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","各层次的质量目标和质量管理职能",true,{"key":16,"text":17,"correct":18},"B","实现质量目标的投资计划",false,{"key":20,"text":21,"correct":18},"C","实现质量目标的进度安排",{"key":23,"text":24,"correct":14},"D","实现质量目标的过程顺序",{"key":26,"text":27,"correct":14},"E","实现质量目标必需的资源","ADE","本题考查的是工程项目质量管理体系。质量计划的内容：（1）明确各层次的质量目标和质量管理职能；（2）明确各层次之间的配合和接口。要做到层次清楚、接口明确、结构合理、协调有效；（3）明确实现质量目标的过程顺序，明确过程中进行质量监测的环节和频率以及标准。根据过程控制的原理按过程顺序进行控制，使每个工序都能保证质量；（4）确定和提供实现质量目标必需的资源；（5）明确记录和报告数据的标准表格。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]