[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938384":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},938384,606,2,"多选题","关于试运行的质量管理，正确的有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","业主方应负责试运行全面组织和指挥",true,{"key":16,"text":17,"correct":14},"B","承包方负责技术服务工作",{"key":19,"text":20,"correct":21},"C","无负荷试运合格后即可进行生产考核",false,{"key":23,"text":24,"correct":21},"D","试运行方案由承包方负责编制",{"key":26,"text":27,"correct":14},"E","试运行人员培训由业主方组织进行","ABE","本题考查的是试运行阶段的工作内容。试运行一般分为无负荷试车和投料试运行两个阶段。无负荷试车必须在机械竣工完成并达到规定要求后进行，也称为竣工试验。无负荷试车成功后，经业主和承包方检查确认具备投料试车条件后方能进入投料试车运行阶段。投料试运行达到规定要求并稳定生产一段时间后开始生产考核。业主方根据承包方的试运行计划和各种资源的供应落实情况编制试运行方案，并取得承包方试运行经理的确认后发布实施。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]