[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938374":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},938374,606,2,"多选题","根据《建设工程项目管理规范》相关规定，下列属于施工质量控制流程的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","确定质量计划",false,{"key":16,"text":17,"correct":18},"B","施工质量目标分解",true,{"key":20,"text":21,"correct":18},"C","施工质量偏差控制",{"key":23,"text":24,"correct":18},"D","施工技术交底与工序控制",{"key":26,"text":27,"correct":18},"E","产品或服务的验证.评价和防护","BCDE","本题考查的是实施阶段质量管理的工作内容。《建设工程项目管理规范》规定，施工质量控制应包括下列流程：（1）施工质量目标分解；（2）施工技术交底与工序控制；（3）施工质量偏差控制；（4）产品或服务的验证、评价和防护",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]