[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938365":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},938365,606,1,"单选题","针对某设计项目建立质量目标，规定质量要求和安排应开展的活动，指的是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","设计策划",true,{"key":16,"text":17,"correct":18},"B","设计评审",false,{"key":20,"text":21,"correct":18},"C","设计控制",{"key":23,"text":24,"correct":18},"D","设计管理","设计策划是指根据合同建立质量目标、规定质量控制要求、安排开展各项设计活动 的计划。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]