[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938360":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},938360,606,1,"单选题","下列不属于质量计划包括的内容的是( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","明确各层次的质量目标和质量管理职能",false,{"key":16,"text":17,"correct":14},"B","明确各层次之问的配合和接口",{"key":19,"text":20,"correct":21},"C","确定和提供制定质量计划所需的资源",true,{"key":23,"text":24,"correct":14},"D","明确记录和报告数据的标准表格","质量计划的内容包括： 1)明确各层次的质量目标和质量管理职能。 2)明确各层次之间的配合和接口。 3)明确实现质量目标的过程顺序，明确过程中进行质量监测的环节和频率以及标准。 4)确定和提供实现质量目标必需的资源。5)明确记录和报告数据的标准表格。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]