[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938358":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},938358,606,1,"单选题","为确保产品能够满足规定的使用要求或已知用途的要求，依据所策划的安排对工程设计进行的认可活动，此为（ ）工作。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","设计策划",false,{"key":16,"text":17,"correct":14},"B","设计评审",{"key":19,"text":20,"correct":14},"C","设计验证",{"key":22,"text":23,"correct":24},"D","设计确认",true,"本题考查的是设计阶段质量管理的工作内容。设计确认是指为确保产品能够满足规定的使用要求或已知用途的要求，依据所策划的安排对工程设计进行的认可活动。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]