[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938348":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},938348,606,1,"单选题","通过对项目投资目标按时间进行分解，在网络计划基础上可做项目进度计划的（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","直方图",false,{"key":16,"text":17,"correct":14},"B","香蕉图",{"key":19,"text":20,"correct":21},"C","横道图",true,{"key":23,"text":24,"correct":14},"D","S曲线","本题考查的是资金使用计划的编制。通过对项目费用目标按时间进行分解，在网络计划基础上，可获得项目进度计划的横道图，并在此基础上编制资金使用计划。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]