[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938346":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},938346,606,1,"单选题","某工程施工到2019年5月31日，已完工作预算投资为8000万元，计划工作预算投资为8500万元，已完工作实际投资为8300万元。则此时的进度绩效指数为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","0.94",true,{"key":16,"text":17,"correct":18},"B","0.96",false,{"key":20,"text":21,"correct":18},"C","1.06",{"key":23,"text":24,"correct":18},"D","1.04","本题考查的是投资偏差分析。SPI＝BCWP\u002FBCWS＝8000\u002F8500＝0.94。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]