[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938341":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},938341,606,2,"多选题","建设投资可分为静态投资部分和动态投资部分。下列属于静态投资的有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","建筑安装工程费",true,{"key":16,"text":17,"correct":14},"B","设备及工器具购置费",{"key":19,"text":20,"correct":21},"C","价差预备费",false,{"key":23,"text":24,"correct":21},"D","建设期利息",{"key":26,"text":27,"correct":14},"E","基本预备费","ABE","本题考查的是工程项目总投资的组成。建设投资可分为静态投资部分和动态投资部分。静态投资部分由建筑工程费、安装工程费、设备及工器具购置费、工程建设其他费和基本预备费构成。动态投资部分，是指在建设期内，因建设期利息和国家新批准的税费、汇率、利率变动以及建设期价格变动引起的建设投资增加额，包括价差预备费、建设期利息等。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]