[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938337":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},938337,606,2,"多选题","资金使用计划的表达方式包括（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","按子项目分解得到的资金使用计划表",true,{"key":16,"text":17,"correct":14},"B","时间－投资累计曲线",{"key":19,"text":20,"correct":21},"C","时标网络图",false,{"key":23,"text":24,"correct":14},"D","综合分解资金使用计划表",{"key":26,"text":27,"correct":21},"E","里程碑法","ABD","本题考查的是资金使用计划的编制。资金使用计划的形式包括按子项目分解得到的资金使用计划表、时间－投资累积曲线、综合分解资金使用计划表。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]