[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938333":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},938333,606,1,"单选题","用赢得值法进行费用、进度综合分析时，需要的基本参数不包括( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","计划工作预算费用",false,{"key":16,"text":17,"correct":14},"B","已完工作实际费用",{"key":19,"text":20,"correct":14},"C","已完工作预算费用",{"key":22,"text":23,"correct":24},"D","全部工作结算费用",true,"用赢得值法进行费用、进度综合分析控制，基本参数有三项，即已完工作预算费用、 计划工作预算费用和已完工作实际费用。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]