[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938332":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},938332,606,1,"单选题","用赢得值法进行费用—进度绩效评价时，若进度偏差大于 0，进度绩效指数大于 1，说明 ( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","进度比计划提前",true,{"key":16,"text":17,"correct":18},"B","进度按计划进行",false,{"key":20,"text":21,"correct":18},"C","进度比计划拖后",{"key":23,"text":24,"correct":18},"D","费用比计划结余","表 费用-进度绩效评价表",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]