[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938318":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},938318,606,1,"单选题","工程量偏差引起合同价款调整，下列说法错误的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","当工程量增加 15%以上时，其增加部分的工程量的综合单价应予调低",false,{"key":16,"text":17,"correct":14},"B","当工程量减少 15%以上时，减少后剩余部分的工程量的综合单价应予调高",{"key":19,"text":20,"correct":21},"C","措施项目按单一总价方式计价，工程量偏差超过 15%时，措施项目费不变",true,{"key":23,"text":24,"correct":14},"D","措施项目按系数方式计价，工程量偏差超过 15%，且该变化引起措施项目相应发生变化，则工程量增加的，措施项目费调增；工程量减少的，措施项目费调减","本题考查的是工程量偏差。如果工程量出现超过15%的变化，且该变化引起相关措施项目相应发生变化时，按系数或单一总价方式计价的，工程量增加的措施项目费调增，工程量减少的措施项目费调减。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]