[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938317":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},938317,606,1,"单选题","某土方工程，招标文件中估计工程量为 1.5 万 m3，合同中约定土方工程单价为 17.5 元／m3，当实际工程量超过估计工程量 15%时，超过部分单价调整为 15.2 元／m3。该工程实际完成土方工程量 1.7 万 m3，则土方工程实际结算工程款为（ ）万元。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","25.84",false,{"key":16,"text":17,"correct":14},"B","28.50",{"key":19,"text":20,"correct":14},"C","29.29",{"key":22,"text":23,"correct":24},"D","29.75",true,"本题考查的是工程量偏差。新单价的调整点为15000×（1+15%）=17250（m3），而本题实际完成的工程量为17000m3，未达到调整点，故实际结算款为17000×17.5=297500（元），即29.75万元。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]