[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938316":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},938316,606,1,"单选题","某工程原定 2018 年 9 月 22 日竣工，因承包人原因，致使工程延至 2018 年 11 月 22 日竣工。当地2018 年 10 月 1 日，因法规的变化导致工程造价增加 100 万元，则其工程合同价款应（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","调增 50 万元",false,{"key":16,"text":17,"correct":14},"B","调减 100 万元",{"key":19,"text":20,"correct":14},"C","调增 100 万元",{"key":22,"text":23,"correct":24},"D","不予调整",true,"本题考查的是法律法规变化。法律法规变化时，因承包人原因导致工期延误的，在合同工程原定竣工时间之后，合同价款调增不予调增，合同价款调减的予以调整（执行“不利于承包人”原则）。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]