[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938311":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},938311,606,1,"单选题","某网络计划中，工作 A 的紧后工作是 B 和 C，工作 B 的最迟开始时间是 14，最早开始时间是 10；工作 C 的最迟完成时间是 16，最早完成时间是 14；工作 A 与工作 B 和工作 C 的间隔时间均为 5 天，工作 A 的总时差为（ ）天。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","3",false,{"key":16,"text":17,"correct":18},"B","7",true,{"key":20,"text":21,"correct":14},"C","8",{"key":23,"text":24,"correct":14},"D","10","本题考查的是制定进度计划的方法。工作 A 的总时差＝5＋2＝7（天）。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]