[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938307":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},938307,606,1,"单选题","已知某工程网络计划如下图所示，该工程工作 E 的最迟开始时间是（ ）。（单位为：天）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","3",false,{"key":16,"text":17,"correct":18},"B","5",true,{"key":20,"text":21,"correct":14},"C","6",{"key":23,"text":24,"correct":14},"D","7","本题考查的是制定进度计划的方法。关键线路为 B－D－F，或①－③－④－⑥。总工期为11 天。故 LFG＝11，LSG＝11－2＝9；LFE＝9，LSE＝9－4＝5。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]