[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938306":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},938306,606,2,"多选题","工程网络计划工期优化的目的是为了( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","缩短计算工期",true,{"key":16,"text":17,"correct":18},"B","寻求资源有限条件下的最短工期",false,{"key":20,"text":21,"correct":18},"C","寻求资源均衡条件下的最优工期",{"key":23,"text":24,"correct":18},"D","寻求最低成本时的最优工期",{"key":26,"text":27,"correct":14},"E","在一定约束条件下使工期最短","AE","工期优化是指压缩计算工期以满足工期要求，或在一定条件下使工期最短的过程。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]