[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938304":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},938304,606,1,"单选题","某工程双代号时标网络计划如下图所示，其中工作 E 的自由时差为( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","0 周",false,{"key":16,"text":17,"correct":18},"B","1 周",true,{"key":20,"text":21,"correct":14},"C","3 周",{"key":23,"text":24,"correct":14},"D","2 周","时标网络计划中：工作自由时差＝波形线在坐标轴上水平投影长度。有例外。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]