[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938303":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},938303,606,1,"单选题","某工程双代号时标网络计划如下图所示，其中工作 A 和 E 的总时差分别为( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","均为 1 月",false,{"key":16,"text":17,"correct":18},"B","分别为 1 月和 2 月",true,{"key":20,"text":21,"correct":14},"C","均为 2 月",{"key":23,"text":24,"correct":14},"D","分别为 2 月和 1 月","N 工作的总时差=min(N 工作所在线路的自由时差之和)",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]