[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938300":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},938300,606,1,"单选题","下列关于双代号时标网络计划的表述中，正确的是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","双代号时标网络计划只能表示工作的开始和完成时间",false,{"key":16,"text":17,"correct":18},"B","虚箭线只能垂直画是因为虚工作的持续时间为零",true,{"key":20,"text":21,"correct":14},"C","时标网络计划宜按各项工作的最晚开始时间编制",{"key":23,"text":24,"correct":14},"D","双代号时标网络计划必须以天为时标单位","A.既能标明计划的时间过程，又能在图上显示出各项工作开始、完成时间、关键线 路和关键工作所具有的时差。 C.时标网络计划宜按各项工作的最早开始时间编制。 D.时标单位可 以是小时、天、周、月、季、年等。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]