[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938299":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},938299,606,1,"单选题","关于双代号时标网络计划的说法，错误的是( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","实箭线的水平投影长度表示该工作的持续时间",false,{"key":16,"text":17,"correct":14},"B","波形线表示工作与其紧后工作之间的时间间隔",{"key":19,"text":20,"correct":21},"C","时标网络计划宜按各项工作的最晚开始时间编制",true,{"key":23,"text":24,"correct":14},"D","双代号时标网络计划以水平时间坐标为尺度进行绘制","C.时标网络计划宜按各项工作的最早开始时间编制。以波形线表示工作与其紧后工 作之间的时间间隔(以终点节点为完成节点的工作除外，当计划工期等于计算工期时，这些工作 箭线中波形线的水平投影长度表示其自由时差)。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]