[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938296":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},938296,606,1,"单选题","某工作网络计划中，N 工作的最早开始时间和最早完成时间分别为第 6 天和第 10 天，最 迟开始时间和最迟完成时间分别为第 9 天和第 13 天，则工作 N 的总时差为( )天。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","5",false,{"key":16,"text":17,"correct":14},"B","4",{"key":19,"text":20,"correct":21},"C","3",true,{"key":23,"text":24,"correct":14},"D","2","N 工作的总时差=N 工作最迟开始-N 工作最早开始 =N 工作最迟结束-N 工作最早结束 时标网络计划中：N 工作的总时差=min(N 工作所在线路的自由时差之和)",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]