[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938294":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},938294,606,1,"单选题","有关里程碑的说法，不正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","里程碑是项目中的关键工作",true,{"key":16,"text":17,"correct":18},"B","里程碑清单列出了所有项目里程碑",false,{"key":20,"text":21,"correct":18},"C","里程碑与常规的进度工作类似",{"key":23,"text":24,"correct":18},"D","里程碑的持续时间为零","本题考查的是工作定义。里程碑是项目中的重要时点或事件。里程碑清单列出了所有项目里程碑，并说明每个里程碑是强制性的（如合同要求的）还是选择性的（如根据历史信息确定的）。里程碑与常规的进度工作类似，有相同的结构和属性，但是里程碑的持续时间为零，因为里碑代表的是一个时间点。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]