[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938292":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},938292,606,2,"多选题","某分部工程双代号网络计划如下图所示，其作图错误包括( )",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","有多个起点节点",false,{"key":16,"text":17,"correct":18},"B","有多个终点节点",true,{"key":20,"text":21,"correct":18},"C","存在循环回路",{"key":23,"text":24,"correct":18},"D","工作代号重复",{"key":26,"text":27,"correct":18},"E","节点编号有误","BCDE","B.有多个终点节点(9\\10)； C.存在循环回路(4\u002F5\u002F6，同时 6-4 工作水平投影向左错 误，6-4 编号错误)； D.工作代号重复(8-9)； E.节点编号有误(6-4)。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]