[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938291":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},938291,606,1,"单选题","在双代号或单代号网络计划中，工作的最早开始时间为其所有紧前工作( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","最早完成时间的最大值",true,{"key":16,"text":17,"correct":18},"B","最早完成时间的最小值",false,{"key":20,"text":21,"correct":18},"C","最迟完成时间的最大值",{"key":23,"text":24,"correct":18},"D","最迟完成时间的最小值","最早开始时间=max(各紧前工作最早完成时间)",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]