[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938287":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},938287,606,2,"多选题","某分部工程双代号网络计划如下图所示，其作图错误包括（ ）",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","有多个起点节点",false,{"key":16,"text":17,"correct":18},"B","有多个终点节点",true,{"key":20,"text":21,"correct":18},"C","存在循环回路",{"key":23,"text":24,"correct":18},"D","节点编号重复",{"key":26,"text":27,"correct":18},"E","节点编号有误","BCDE","本题考查的是工作顺序安排。本图存在有多个终点节点（⑨⑩）；本图存在循环回路（④⑤⑥）、同时⑥→④ 工作水平投影向左错误，⑥④编号错误）；本图节点编号重复（⑧）。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]