[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938286":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},938286,606,1,"单选题","工程项目进度计划的优化方法有( )种。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","1",false,{"key":16,"text":17,"correct":14},"B","2",{"key":19,"text":20,"correct":21},"C","3",true,{"key":23,"text":24,"correct":14},"D","4","进度计划的优化方法有：工期优化、费用优化和资源优化三种。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]