[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938282":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},938282,606,1,"单选题","根据 FIDIC《施工合同条件》，承包商未能在规定时间内修复缺陷工程部位，业主可雇用他人完成，费用从（ ）内扣除。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","保留金",true,{"key":16,"text":17,"correct":18},"B","工程进度款",false,{"key":20,"text":21,"correct":18},"C","预付款",{"key":23,"text":24,"correct":18},"D","履约保证金","本题考查的是 1999 版 FIDIC 施工合同条件的主要内容。合同内以履约保函和保留金两种手段作为约束承包商忠实履行合同义务的措施，当承包商严重违约而使合同不能继续顺利履行时，业主可以凭履约保函向银行获取损害赔偿；而因承包商的一般违约行为令业主蒙受损失时，通常利用保留金补偿损失。例如，承包商未能在工程师规定的时间内修复缺陷工程部位，业主雇用其他人完成后，这笔费用可从保留金内扣除。履约保函和保留金的约束期均是承包商负有施工义务的责任期限（包括施工期和保修期）。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]